Microsoft 070-178 certification exam has become a very influential exam which can test computer skills.The certification of Microsoft certified engineers can help you to find a better job, so that you can easily become the IT white-collar worker,and get fat salary.
However, how can pass the Microsoft 070-178 certification exam simple and smoothly? DumpLeader can help you solve this problem at any time.
DumpLeader is a site which providing materials of International IT Certification. DumpLeader can provide you with the best and latest exam resources.The training questions of Microsoft certification provided by DumpLeader are studied by the experienced IT experts who based on past exams. The hit rate of the questions is reached 99.9%, so it can help you pass the exam absolutely. Select DumpLeader, then you can prepare for your Microsoft 070-178 exam at ease.
In order to facilitate candidates' learning, our IT experts have organized the 070-178 exam questions and answers into exquisite PDF format. Before your purchase, you can try to download our demo of the 070-178 exam questions and answers first. You will find that it is almost the same with the real 070-178 exam. How it can be so precise? It is because that our IT specialists developed the material based on the candidates who have successfully passed the 070-178 exam. And we are checking that whether the 070-178 exam material is updated every day.
The 070-178 study materials of DumpLeader aim at helping the candidates to strengthen their knowledge about TS. As long as you earnestly study the 070-178 certification exam materials which provided by our experts, you can pass the TS 070-178 exam easily. In addition, we are also committed to one year of free updates and a full refund if you failed the exam.
Perhaps many people do not know what the Testing Engine is, in fact, it is a software that simulate the real exams' scenarios. It is installed on the Windows operating system, and running on the Java environment. You can use it any time to test your own 070-178 simulation test scores. It boosts your confidence for 070-178 real exam, and will help you remember the 070-178 real exam's questions and answers that you will take part in.
The 070-178 VCE Testing Engine developed by DumpLeader is different from the PDF format, but the content is the same. Both can be used as you like. Both of them can help you quickly master the knowledge about the TS certification exam, and will help you pass the 070-178 real exam easily.
TS 070-178 training materials contains the latest real exam questions and answers. It has a very comprehensive coverage of the exam knowledge, and is your best assistant to prepare for the exam. You only need to spend 20 to 30 hours to remember the exam content that we provided.
DumpLeader is the best choice for you, and also is the best protection to pass the Microsoft 070-178 certification exam.
All the customers who purchased the Microsoft 070-178 exam questions and answers will get the service of one year of free updates. We will make sure that your material always keep up to date. If the material has been updated, our website system will automatically send a message to inform you. With our exam questions and answers, if you still did not pass the exam, then as long as you provide us with the scan of authorized test centers (Prometric or VUE) transcript, we will full refund after the confirmation. We absolutely guarantee that you will have no losses.
Easy and convenient way to buy: Just two steps to complete your purchase, then we will send the product to your mailbox fast, and you only need to download the e-mail attachments.
Microsoft Project 2010, Managing Projects Sample Questions:
1. Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday. John, a team member, asks to take Thursday off from work. He will work on Saturday to adjust this time. You need to ensure that the change in John's working time is reflected in the project schedule. What should you do?
A) In the Resource Information window for John, select the inactive option for Thursday and cancel the selection of the inactive option for Saturday.
B) In the Resource Information window for John, change John's availability by modifying the Available From and Available To dates for Thursday to 0 percent and for Saturday to 100 percent.
C) Update the project calendar for John by making Thursday as a non-working day and Saturday as a working day.
D) Update the resource calendar for John by making Thursday as a non-working day and Saturday as a working day.
2. A section of your project contains only a summary task along with four subtasks and a milestone. You discover that the section is located in the incorrect phase and has the incorrect Work Breakdown Structure (WBS) numbering. You need to move the section to another phase of the project. You also need to ensure that the section reflects the correct WBS numbering. What should you do?
A) Modify the start and finish dates of the summary task.
B) Select the summary task and change the scheduling mode to Manually Scheduled.
C) Drag the summary task.
D) Select the entire section and click Move Task.
3. You need to view the following information for your project: ?Current cost ?Baseline cost ?Actual cost ?Remaining cost ?Percentage of completion Which component will display the information?
A) The Project Statistics window
B) The default Resource Sheet
C) The default Task Sheet
D) The default Cost Table
4. Your customer wants to receive your project's Timeline view in a document by e-mail. You need to create a document that contains only the Timeline view. You select the Timeline view. What should you do next?
A) Select Visual Reports.
B) Select Save View.
C) Select Sync With Task List.
D) Select Create PDF/XPS Document.
5. You have two dependent tasks named Task 1 and Task 2. Task 1 is the predecessor for Task 2. You need to ensure that when the duration of Task 1 changes, the scheduled start date for Task 2 does not change automatically. How should you configure Task 2?
A) Set the constraint type to Start No Earlier Than.
B) Set the lag to two elapsed days (2ed).
C) Set the task type to Fixed Duration.
D) Set the schedule mode to Manually Scheduled.
Solutions:
Question # 1 Answer: D | Question # 2 Answer: C | Question # 3 Answer: A | Question # 4 Answer: A | Question # 5 Answer: A |